Laying wooden claddingis the set of operations that consist of fixing wooden boards to a secondary framework (the battens) in order to clad and protect the façade of a building. It is a technically demanding piece of work that determines the durability and the performance of the entire envelope of a house or building. Badly carried out, wooden cladding becomes a moisture trap, a source of premature rot and water infiltration.

wdwsWould you like to make sure you lay your wooden cladding properly so that it lasts? WoodPartners takes you through every step of laying wooden cladding by the book: choice of materials, direction of laying, framework, ventilation, fixings and finishes.

Laying wooden cladding in brief

  • Laying wooden cladding consists of fixing wooden boards to a framework of battens in order to clad and protect the façade of a building.

  • Laying takes place in 4 steps: prepare the site, lay the breather membrane and the battens, ensure ventilation, then fix the boards.

  • Horizontal laying is simpler and less expensivethan vertical laying, which offers better water run-off but requires double battening.

  • The fixings must be made of stainless steel with ring-shank nails.

  • The price of laying wooden cladding per m² is on average 80 to 100 € supply and installation included, depending on the species and the complexity of the job.

Laying wooden cladding consists of fixing wooden boards to a façade in order to protect it.

What is the role of wooden cladding?

Wooden cladding is a façade covering made up of boards (also called weatherboards) that overlap or slot into one another. These boards are not fixed directly to the façade, but to a load-bearing framework fixed to the wall. Natural wood cladding is very widespread but it can also be in composite wood or PVC.

Wooden cladding fulfils three essential functions:

  • Climate protection: the cladding is the first line of defence against the weather (driving rain, wind, UV). Even though it is not the main weatherproofing element (that role falls to the breather membrane), it protects the façade from direct attack.

  • Thermal improvement: in combination with external thermal insulation (ITE), wooden cladding significantly improves the energy performance of a building.

  • Architectural enhancement: wood brings a natural and contemporary look, infinitely variable according to the species, the shade and the direction in which the wooden cladding is laid.

Worth knowing

Laying wooden cladding differs from laying composite, PVC or aluminium cladding: the materials, the fixings and the installation rules are not the same.

Which tools do you need to lay wooden cladding?

Before you start laying wooden cladding, make sure you have the following equipment:

Tool

Use

Spirit level / laser level

Check that the rows are horizontal and the battens vertical

Chalk line

Mark out the starting line 20 cm from the ground

Circular saw or mitre saw

Cut the boards precisely

Pneumatic nailer or screwdriver

Fix the boards to the battens

Moisture meter

Check the moisture content of the wood (max. 19%)

Construction stapler

Fix the breather membrane to the substrate

Sacrificial block

Slot the boards together without damaging the tongues

Carpenter’s square

Check the angles and the cuts

Tape measure and carpenter’s pencil

Measuring and marking out

To fix the battens to a masonry substrate (concrete block, concrete), also allow for a hammer drill and hammer-in anchors (10×180 mm type). On a timber frame, stainless steel construction screws are enough.

How do you lay wooden cladding?

Laying wooden cladding takes place in 4 main steps:

  • Prepare the site

  • Weatherproof the façade

  • Ensure the ventilation of the external wooden cladding

  • Fix the cladding

Step 1 – Prepare the site

Once you have chosen your cladding, preparing the site consists of checking several things before the cladding is laid:

  • Check that the supporting wall is sound, that is to say that it has no cracks, no damp and no crumbling areas that would prevent the battens from being fixed securely. The framework must be able to be anchored to a solid substrate that will not deteriorate once covered.

  • Check that the substrate is flat, because a bulging or hollow wall will show through the whole framework and the final look of the boards.

  • Check the moisture content of the boards with a moisture meter. Ideally, the moisture content should not exceed 19% at the time of laying.

  • Attend to the calculation and the ordering of the materials: it is important to make sure you have enough wooden boards so that the work does not have to be interrupted. You should generally allow 10 to 15% extra boards to make up for the losses due to cutting.

  • Measure the area to be covered and calculate the quantities of boards, battens and breather membrane, with the margin for offcuts

  • Store the boards correctly: it is recommended that you have the wood delivered in advance and store it under a ventilated shelter, raised off the ground so that it does not touch it.

  • Mark out the reference lines : The first direct action on the wall consists of marking out the starting line (generally using a chalk line). This line must be located at least 20 to 30 cm from the ground in order to protect the future cladding from damp and splashes.

 Laying wooden cladding takes place in 4 steps. The first is preparing the wall.

Step 2 - Weatherproofing the façade for lasting cladding

The weatherproofing step is made up of 2 operations: laying the breather membrane and putting the batten framework in place.

The breather membrane

The breather membrane is compulsory behind the cladding, on every substrate (timber frame, brick, concrete block), unless the supporting wall is already considered weatherproof (for example, a poured concrete wall). The cladding protects the building but it is the breather membrane whose primary role is to ensure complete weatherproofing.

The breather membrane protects the structure from water infiltration and lets the water vapour from inside escape:

  • The breather membrane used must be flexible and permeable to water vapour(with an Sd value of less than 0.18 m) to allow the façade to breathe

  • The breather membrane film is laid directly on the wall, before the wooden framework is built

  • To avoid any water infiltration, the strips of breather membrane are not laid edge to edge, but must overlap. The standard (DTU 41.2) generally requires a minimum overlap of 5 cm (50 mm) horizontally and 10 cm (100 mm) vertically

  • To optimise overall air and water tightness, it is strongly advised that these overlap areas be bonded or taped using adhesive strips

The breather membrane is compulsory behind the cladding to protect the structure from water infiltration.

The framework, also called battening

The battens form the load-bearing structure to which the boards are fixed. We recommend that you use wooden battens of use class 2 minimum and ideally class 3 or 4 for greater resistance.

As regards the centre-to-centre spacing, that is to say the distance between 2 battens, we recommend:

  • If the battens are spaced 40 cm apart or less, a 22×45 mm batten is enough.

  • If the battens are spaced up to 65 cm apart, a 27×65 mm batten is needed, thicker and wider to bear the load.

Worth knowing

To lay wooden cladding on concrete blocks, fix the battens with hammer-in anchors (10×180 mm type) so as to anchor firmly into the second wall of the block. Always check that the substrate is flat before laying the framework, because any irregularity in the wall will be amplified at the surface.

The battens form the load-bearing structure to which the boards are fixed.

Step 3 - Ensuring the ventilation of external wooden cladding

Ventilation allows external wooden cladding to have air circulating continuously so as to prevent moisture from sitting behind the boards and causing premature rot of the wood and the framework.

Ventilation rests on several technical principles governed by the DTU 41.2 construction standard:

  • Creation of an air gap of at least 20 mm behind the cladding boards.

  • For the ventilation to be effective and for the air to circulate from bottom to top, you have to provide air inlets at the foot of the cladding and air outlets at the top of the façade. The area of these openings must be at least 50 cm² per linear metre for a standard façade

  • Installing rodent guards: these are perforated metal profiles that are fixed to the air inlets and outlets and that guarantee ventilation while blocking the intrusion of small animals.

  • Ground clearance : this is what the first board laid is called; it must be located at least 20 cm from the finished ground level.

Ventilation allows external wooden cladding to have air circulating continuously.

Step 4 – Fixing the wooden cladding

When laying wooden cladding,fixing consists of anchoring the boards (or weatherboards) firmly to the batten framework installed beforehand. This step guarantees that the façade will withstand wind, weather and the natural movement of the wood.

To this end, fixing follows precise technical rules:

  • The choice of fixing materials : it is imperative to use screws or ring-shank nails (or serrated nails) in stainless steel, galvanised steel or aluminium alloy so as to avoid black rust runs appearing. Smooth-shank nails are strictly forbidden because, under the effect of the swelling/shrinking cycles of the wood, they end up working their way out.

  • Slotting together and the direction of laying: Fixing is generally carried out from the bottom of the wall upwards for vertical laying. In the case of horizontal laying, the tongue of the board must always face upwards to prevent rainwater from getting in. The boards must slot together while keeping a slight free gap to allow the wood to expand and contract naturally.

  • The anchoring depth : To ensure good wind resistance, the fixings must penetrate at least 22 mm into the wood of the batten. The total length of the fixing should be about 2.5 times the thickness of the board.

  • The number of fixings : It varies according to the width of the board laid. For thin boards (up to 100 or 125 mm of visible width depending on the profile), a single fixing at each crossing with a batten is enough. For boards more than 125 mm wide, on the other hand, two visible fixings per crossing must be used.

fixing consists of anchoring the boards firmly to the battens installed beforehand

Free, no commitment Describe your project, suppliers reply.

One form, several offers.

  • Two minutes, no account
  • Direct, no middleman
  • Your identity stays private
Describe my project

What mistakes should be avoided when laying wooden cladding?

Here are the most frequently encountered mistakes when laying wooden cladding:

  • Overlooking the moisture content of the wood : this is the number one cause of problems, because badly laid cladding creates irreversible moisture-related problems once the boards are fixed.

  • Forgetting the ground clearance : a first board that is too close to the ground is regularly in contact with splashing water and damp, and will rot prematurely.

  • Using untreated steel fixings : rust runs stain the boards permanently and are impossible to remove without sanding.

  • Not protecting the cuts : every cut in a board exposes the wood fibres. Without a fungicidal treatment and a finish on the ends, moisture travels up through the whole board by capillary action.

  • Blocking the ventilation: laying vertical wooden cladding without double battening, or fitting rodent guards that are too fine, traps moisture behind the boards.

  • Ignoring the width/thickness ratio of the boards : a board that is too wide in relation to its thickness will inevitably cup under the effect of wet/dry cycles.

  • Lining up the end joints: joints lined up vertically weaken the façade and harm its appearance. Always lay them staggered.

Laying wooden cladding takes place in 4 steps that must be followed meticulously

Horizontal or vertical cladding: which direction of laying should you choose?

The choice between horizontal or vertical cladding depends above all on the look you want and on your budget:

  • Horizontal laying is simpler to carry out, less expensive and gives the façade a widened effect.

  • Vertical laying offers better water run-offand a more contemporary result, but it requires double battening, which makes the framework more complex and increases the cost by 10 to 15%.

The choice between horizontal or vertical cladding depends on the look you want and on your budget

Laying wooden cladding horizontally

This is the most widespread configuration in France. It visually stretches the building and makes it easier for water to run off naturally. From a technical point of view, here is what it involves:

  • The tongue must always face upwards so as to create a natural drip effect that prevents water from sitting in the groove and causing rot from the inside.

  • The framework is made up of simple vertical battens, perpendicular to the boards.The spacing (or centre-to-centre distance) between these vertical battens is generally between 40 and 65 cm maximum, depending on the thickness of the boards used.

  • The laying of the wooden boards always starts at the bottom of the wall and works gradually up towards the top of the façade.

Laying wooden cladding vertically

This method is very much in fashion, because it gives the façade a slender, contemporary look and it offers the best water run-off. It is, however, more technically demanding because it calls for double battening: a first network of vertical battens fixed to the wall creates the air gap, then a second network of horizontal battens is fixed over the top to act as a support for the boards.

Criterion

Horizontal laying

Vertical laying

Water run-off

Good (tongue facing up)

Excellent (directly by gravity)

Framework required

Simple vertical battens

Double battening compulsory

Complexity of laying

Moderate

More technical

Visual result

Building widened

Building made slender

Trend

Classic / American

Contemporary / Scandinavian

Framework cost

Standard

+10 to 15% (double battens)

Which board thickness should you choose when laying wooden cladding?

The thickness of the boards is governed by the width/thickness ratio, which requires that the wider a board is, the thicker it must be to stay stable. So the visible width of the board must not exceed 7.5 times its thickness. For Red Cedar and larch (more stable species): the ratio can go up to 10 times the thickness.

The wider a board is, the more it will move (swell/shrink) as the seasons change. If it is too wide in relation to its thickness, it does not have enough rigidity to withstand these movements and it will distort.

In practice:

  • A board 20 mm thick can be up to 150 mm wide (that is 7.5 × 20).

  • A board 22 mm thick can be up to 165 mm wide.

Laying wooden cladding successfully calls for a fine understanding of the interactions between wood and its environment. By following the DTU 41.2 standard on the 20 cm ground clearance, ventilation, stainless steel fixings and controlled moisture content, you guarantee that a cladding job will last.

WoodPartners supports you in choosing the materials and puts you in touch with qualified professionals from the timber industry to make your project a reality.

For wooden cladding, the visible width of the board must not exceed 7.5 times its thickness